✓   3M Woodlands AF8 Up-grading Project

This project involves diversion and removal of some existing Mechanical, Electrical and Process (MEP) services at Catwalk 7, 8 and Compounding Area to make way for new clean production room and addition of a Class 10K cleanroom.

Scope include Micro Piling, erection of a bondek (Civil & Structural) Mechanical System include HVAC system, Carbon Filter System, High Pressure Compressed Air system, Electrical System, Data Network, Life Safety System, Fire Alarm & Fire Protection System, PA, CCTV & Card Access System.

 

REC is a leading vertically integrated solar energy company

 

✓   DWS Fan-out Facilities & Utilities A/A

This project involves the design and conversion of an existing Slurry System to Coolant System for Wafer Wire Saw Process. Our scope comprises of Mechanical, Electrical, Instrumentation and CSA works. The CSA work involves Back Filling of existing Pit and Construction of a new Shed to house a new Filter Press Unit.

 ✓   REC 1D Building Expansion

This project involves the design and construction of a 6,500m² 100K cleanroom with utilities (Civil & Structural, Mechanical System, DIW & Waste Water System, Gas & Chemical System, Electrical System, Data Network, Life Safety System, Fire Alarm & Fire Protection System, PA, CCTV & Card Access System)

 

One of the world’s leading flavour and fragrances producing company

 

   Design & Building of HVAC system

Engineering calculations of duct works plus sizing of fan & MA

Develop air balancing strategy and executions

Installation of fans & MAU Systems (piping & ducting)

Test & commissioning for normal and fire mode

   Reinstatement of Ex-FR Area 

Modification of Existing production space to FR area (990m2)

Modification of existing services, adding of new services to FR area (include Civil, Structural & Architectural Work, Fire Protection System, Mechanical System, Electrical System, ELV System)

Fab 10A

Semiconductor leader in innovative memory solutions of DRAM, NAND, NOR and 3D XPoint Memory

 

 

 

 

✓     Chilled Water System for FAB Building

✓     HK21  Mechanical Hook Up for Tool Install

✓     HK08 & HK11 Racking & Raised Floor for Tool Install

✓     Supply Chain Management (Hook-up Phase)

✓     Fabrication of Modular Rack (Hook-up Phase)

 

Fab 10X

 

✓      Chilled Water System for Admin Building

✓      New PCW system

✓      Complete Mechanical, Electrical and Plumbing package for Soxal Gas Yard

✓      Supply Chain Management (Hook-up Phase)

✓      Fabrication of Modular Rack (Hook-up Phase)

✓      Fabrication of PCW water assembly (Hook-up Phase)

✓      HK23 – Drain Hook Up for Tool Install

✓      HK08 & HK11 – Racking & Raised Floor for Tool Install

 

Fab 10N

 

✓      Chilled water work for electrical room FCU

✓      Dry-coil replacement work

✓      Hook-up of Exhaust and Hi-vac system

✓      Supply and install of natural gas line for VOC system

✓      In-line Param Process Drain

✓      North Wing Expansion Process Drain

✓      Natural Gas expansion project

✓      MAU assembly and piping installation

✓      HFW and SWFD process drain

✓      SWW lift station upgrade

✓      Acid exhaust expansion project

✓      Relocate Dry Coil

✓      Addition of 1no Chiller, 1no Cooling Tower and 1no of MAU

✓      New Loop 3 PCW Plant

 

(Formerly known as Heptagon)

Global leader in the design & manufacture of advanced sensor solutions

 

      7000 AMK

Design and Construct Level 3, L4, L5 Office & L1M Break Room (Total Area 8,000m2)

Scope of Work:  Civil, Structural & Architectural Works, System Furniture, Mechanical & Electrical System, Equipment

✓      AMS Woodlands

Design and Construct Level 1, L2, L4 Office & Canteen (Total area 1,000m2)

Scope of Work:  Civil, Structural & Architectural Works, System Furniture, Mechanical & Electrical System, Equipment

 

One of the world’s leading silicon wafers manufacturers

 

 

✓     Addition of 2no booster pumps for Condenser system and 1no Cooling Tower for CZ Building

✓     Exhaust hook-up

Industry-Leading RF Front-End Solutions for Mobile Devices

 

 

 

 

✓     Acid Exhaust Duct Work for New Scrubber System

✓     CDA Plant Room Fit Up

A research institute that aims to enhance the value-add of the microelectronics industry in Singapore

 

 

 

 

✓    Supply & Installation of 46 nos of Specialty & Bulk Gases

✓    Distribution system for 3 Clean rooms

Opto-Pharm is a Sterile Pharmaceutical and Contact Lens Care Solutions manufacturer

 

 

 

✓    Provide solutions to resolve existing cleanroom environmental control (temperature, RH, etc.)

✓    M&E works for upgrading of tanks (electrical, piping, controls, HVAC, etc.)

✓    Replacement of Chilled Water Piping

✓    Design and Built Clean room

 